Yambaling Hydropower Limited (YHL) was incorporated on November 21, 2007 as a private limited company. Its paid-up capital, as of mid-September 2019, was ~NPR 125 million (of which ~NPR 76 million has been certified by the Office of Company Registrar in March 2019), fully held by the promoters. YHL is developing the 7.27-MW Yambaling Khola HPP in Sindhupalchowk district, Bagmati Province of Nepal at a budgeted cost of NPR 1,200 million at a debt:equity ratio of 70:30. The project is a run-of-river (R-o-R) type and is being developed at 40% probability of exceedance (Q40). The contract PLF is ~59% with an annual production capacity of ~38 GWh of energy with a dry energy mix of ~18%. The major promoters are also operating the 5-MW Pikhuwa Khola Small Hydropower Project under Eastern Hydropower Limited.

Salient Features

Project Name: YambalingKhola Hydropower Project
Development Region: Central Development Region
District: Sindhupalchok
Location of Project Site: Gumba VDC
Water Source: YambalingKhola
Type of Scheme: Run off River
Access Road: Existing Road-Kathmandu-Balephi-Jalbire-Black topped Road, Jalbire-Kattike-Manje-Bolde to project site Gravel Road
Installed Capacity: 7.27 MW
Gross Head: 798.00 m
Rated Design Head: 752.90 m
Design Plant Discharge: 1.14 m3/sec at Q40%

Catchment Area: 14.15 sq. km
Average Precipitation:
3595 mm/year
100 years Design Flood (HW): 53 m3/sec
Minimum Monthly Flow: 0.231 m3/sec
Design Discharge: 1.14 m3/sec (Q40%)
Riparian Release Intake: 0.03 m3/sec